Project 3
Updated
Sunday, October 21, 2007 01:37:25 PM.
The Due Date is Monday November 5, 10:30 am. Project 3 should be a single Word
file. E-mail as an attachment to to the class e-mail account
eng_0052@engineering.uiowa.edu
(Late fees apply. Do check that the Word file is attached.)
See the web pages on the project and
project report for background
information.
Remember that a highly professional standard is required. Use page numbers.
Include the names of project team members at the start of the document.
Give sources for any drawings etc.
Your task in this homework is to produce:
A. A Detailed Proposed Design
This involves determining a detailed proposed design, based on your
assessment of the existing designs, your testing of your initial design and on the materials available for the
project.
You will need to produce a drawing of the proposed design and describe it's main features. The drawing can be drawn, scanned and then pasted into
the Word document. Alternatively you can use a computer drawing program.
Describe the reasons that you decided on this design.
Grades will be awarded based on the quality and depth of the design
rationale.
B. An Economic Analysis
Costs - The total cost of the design can be calculated as
follows:
Each girder (aka each craft stick) including
purchasing, transport and inspection |
$1,150 |
Each short joint (less than 1/3 of the length of a girder)
|
$375 |
Each long joint (across more than 1/3 of the length of a
girder) |
$500 |
Water tank |
$35,000 |
Site preparation, water connections and access |
$60,000 |
Planning |
$35,000 |
Receipts - The expected receipts (in current dollars) from the
operation of the tower are as follows
Year |
1 |
2 |
3 |
4 |
5 |
Receipts ($) |
55,000 |
85,000 |
90,000 |
95,000 |
100,000 |
Economic Analysis Calculation: Given the above, calculate
the Net Present Value and the Internal Rate of Return, assuming an interest
(discount) rate of 8%. The costs can be assumed to occur in Year 0. The NPV
and IRR are to be calculated in Year 0.
You will need to produce an Excel spreadsheet to do this
portion. Paste, using Paste Special, as an Excel object into your Word file.
Grades will be awarded based on the quality and depth of the
economic
rationale.
C.
Expected Performance of Design
Give, with reasons, the anticipated final load bearing capacity of your
design.
|